Netherlands > Groningen

Groningen grid status

Groningen is the mirror image of the congested south: the transmission grid mostly has off-take room while feed-in is the binding constraint, driven by solar, wind and offshore landing. The largest feed-in waiting lists sit at Delfzijl (about 83 MW) and Veendam (about 63 MW). Eemshaven is the exception within the exception, an industrial and offshore-landing area with room in both directions and the largest TenneT build-out. Enexis is the sole regional grid operator for the sampled areas.

Off-take: Partial Feed-in: Congested

Commercial read

What is constrained: Feed-in across most of the province: the transmission grid has off-take room while feed-in is at its most constrained level in most sampled areas. The largest feed-in waiting lists sit at Delfzijl (about 83 MW) and Veendam (about 63 MW).

Still worth screening: Off-take: the transmission off-take layer generally has headroom, so an industrial or datacentre load faces a very different picture than a solar or wind project. Eemshaven is the standout, an industrial and offshore-landing area with room in both directions and the largest TenneT build-out.

What changed: Enexis announced (31 October 2025) six new high-voltage stations in Groningen, including Eemshaven Oostpolder, Farmsum Oosterlaan and Meerstad, plus expansions at Vierverlaten, Weiwerd and Stadskanaal, part of its largest-ever reinforcement.

What to watch: The northern TenneT build-out (Eemshaven Oostpolderweg 380/110 kV 2034 to 2037, Farmsum Oosterlaan 2032 to 2035, Vierverlaten 380/110 kV 2034 to 2036) and whether the Delfzijl and Veendam feed-in queues move as regional expansions land.

The numbers

83.1MW Feed-in capacity on the waiting list at the Delfzijl (Weiwerd) service area

source, as of 2026-07-05

62.6MW Feed-in capacity on the waiting list at the Veendam service area

source, as of 2026-07-05

Stations and areas

  • Province overview, directional: Every Groningen service area Wattlas sampled on 5 July 2026 shows TenneT's off-take layer at a less constrained level (code 1) while the feed-in layer is at its most constrained level (code 3), except Eemshaven and Delfzijl where both layers have room. This is the reverse of the congested south: off-take generally has headroom, feed-in is the binding constraint. Expected: Feed-in relief runs through the large TenneT northern build-out (Eemshaven Oostpolderweg 2034 to 2037, Farmsum Oosterlaan 2032 to 2035, Vierverlaten 2034 to 2036), so these three span 2032 to 2037; related regional works in the same programme run to 2039. source
  • Delfzijl (Weiwerd) service area, feed-in: The capacity map (sampled 5 July 2026) lists 509.1 MW existing against 399.7 MW required feed-in capacity with an 83.1 MW feed-in waiting queue, the largest in the sampled Groningen areas, on an industrial-scale grid (off-take existing 518 MW). TenneT code 0 both layers here, so the constraint is regional feed-in capacity rather than transmission. Expected: TenneT Farmsum Oosterlaan 220/110 kV (2032 to 2035) and Eemshaven Oostpolderweg 380/110 kV (2034 to 2037); Enexis expands Weiwerd. source
  • Veendam service area, feed-in: The capacity map (sampled 5 July 2026) lists 154.7 MW existing against 107.8 MW required feed-in capacity with a 62.6 MW feed-in waiting queue, TenneT feed-in code 3, regional solve indicated 2029. Off-take has room (existing 155.4 against 61.5 required). Expected: Regional feed-in solve indicated 2029; TenneT Meeden-Winschoten 110 kV and Gasselte-Veendam works 2029 to 2037. source
  • Eemshaven service area, both directions: The capacity map (sampled 5 July 2026) lists 149.8 MW existing against 70 MW required off-take (queue 0.1 MW) and 155.5 MW existing against 123 MW required feed-in (queue 0 MW), with TenneT off-take code 1 and feed-in code 0. Eemshaven has room in both directions, unusual for the north, and carries the largest TenneT build-out: a new Eemshaven Oostpolderweg 380/110 kV station. Expected: New TenneT 380/110 kV station Eemshaven Oostpolderweg (2034 to 2037) and Farmsum Oosterlaan (2032 to 2035). source

Capacity detail per station or area

Station or area Layer Direction Available MW Needed MW Relief project Confidence Source
Province overview, directional Both grids Feed-in Not yet published Not yet published Eemshaven Oostpolderweg 380/110 kV, Farmsum Oosterlaan 220/110 kV, Vierverlaten 380/110 kV (TenneT), 2032 to 2037 for the three named stations, indicative; related regional works run to 2039 high source, 2026-07-05
Delfzijl (Weiwerd) service area, feed-in Regional (DSO) Feed-in 509.1 399.7 Farmsum Oosterlaan and Eemshaven Oostpolderweg (TenneT) plus Weiwerd expansion (Enexis), 2032 to 2037, indicative high source, 2026-07-05
Veendam service area, feed-in Both grids Feed-in 154.7 107.8 Meeden-Winschoten 110 kV and Gasselte Kraanlanden-Veendam works (TenneT), 2029 to 2037, indicative high source, 2026-07-05
Eemshaven service area, both directions Both grids Both 149.8 70 Eemshaven Oostpolderweg 380/110 kV and Farmsum Oosterlaan 220/110 kV (TenneT), 2032 to 2037, indicative high source, 2026-07-05

Intelligence on this region

Sources

As of 2026-07-05. All MW figures come from the official Netbeheer Nederland capacity map, sampled 5 July 2026, carrying that peildatum; existing, required and queued capacity are the map's published per-service-area figures. The directional flip (off-take room, feed-in constrained) is confirmed across the sampled areas. Enexis build-out figures come from Enexis' own press release of 31 October 2025. TenneT project dates are from the capacity map projects layer, all indicative operator timelines. Enexis is the sole regional grid operator for the sampled Groningen areas.

Forward internally

Forward this internally if your team is asking: is Groningen worth screening right now, which layer is constrained, and what changed last. https://wattlas.eu/netherlands/groningen

Founding access

Founding access adds: source-backed updates as they emerge, priority region requests, early capacity-change updates, company-level use, priority access to future exports and snapshots.

Want Wattlas to track this region for your team?

Request founding access