Commercial read
What is constrained: Feed-in across the province: the transmission grid has off-take room while feed-in is at its most constrained level. The largest feed-in waiting list sits at Emmen (about 71 MW), with Norg around 46 MW.
Still worth screening: Off-take: the transmission off-take layer generally has headroom, so an industrial or datacentre load faces a different picture than a solar or wind project. Note that Hoogeveen has a real off-take queue (about 44 MW) on the regional grid despite the transmission off-take headroom.
What changed: Enexis announced (31 October 2025) eight new stations for the Drenthe area, including Musselkanaal, Veenoord Boerdijk and Meppel Noord, part of its largest-ever reinforcement. TenneT's Musselkanaal 380/110 kV station is in progress for 2026.
What to watch: The TenneT northern reinforcement (Musselkanaal 2026, Veenoord Boerdijk 380 kV 2031 to 2034, Deelnet Emmen 2031 to 2033), the Rendo new station at Hoogeveen, and whether the Emmen feed-in queue moves.
The numbers
source, as of 2026-07-05
source, as of 2026-07-05
Stations and areas
- Province overview, directional: Every Drenthe service area Wattlas sampled on 5 July 2026 shows TenneT's off-take layer at a less constrained level (code 1) while the feed-in layer is at its most constrained level (code 3). As in Groningen, off-take generally has headroom while feed-in is the binding constraint. Expected: Feed-in relief runs through the TenneT northern reinforcement (Musselkanaal 2026, Veenoord Boerdijk 380 kV 2031 to 2034, Drents Overijsselse Netversterking 2033 to 2036). source
- Emmen (Bargermeer) service area, feed-in: The capacity map (sampled 5 July 2026) lists 82.5 MW existing against 60.8 MW required feed-in capacity with a 71.1 MW feed-in waiting queue, the largest in the sampled Drenthe areas, TenneT feed-in code 3, regional solve indicated 2030. Off-take has room (existing 94.1 against 64.5 required). Enexis plans extra capacity on Bargermeer in 2030. Expected: Enexis extra capacity Bargermeer 2030; TenneT Deelnet Emmen 2031 to 2033 and Veenoord Boerdijk 2031 to 2034. source
- Norg (Zeyerveld) service area, feed-in: The capacity map (sampled 5 July 2026) lists 207 MW existing against 125 MW required feed-in capacity with a 46.3 MW feed-in waiting queue, TenneT feed-in code 3, regional solve indicated 2026. Off-take has ample room (existing 208.4 against 72.3 required). Expected: Enexis extra capacity Zeyerveen (approved, between 2022 and 2026); TenneT Zeyerveen 220 kV transformers 2029 to 2030. source
- Hoogeveen service area, both directions: The capacity map (sampled 5 July 2026) lists 103.8 MW existing against 86.7 MW required off-take (queue 44.5 MW, regional solve 2025) and 97.5 MW existing against 109.6 MW required feed-in (queue 9.1 MW, solve 2027). This service area sits on an Enexis and Rendo boundary, with a Rendo project for a new high-voltage station (afname 2028, opwek 2030). Expected: Rendo new high-voltage station (off-take 2028, feed-in 2030); Enexis extra capacity Hoogeveen (between 2022 and 2027). source
Capacity detail per station or area
| Station or area | Layer | Direction | Available MW | Needed MW | Relief project | Confidence | Source |
|---|---|---|---|---|---|---|---|
| Province overview, directional | Both grids | Feed-in | Not yet published | Not yet published | Musselkanaal 380/110 kV, Veenoord Boerdijk 380 kV, Drents Overijsselse Netversterking (TenneT), 2026 to 2036, indicative | high | source, 2026-07-05 |
| Emmen (Bargermeer) service area, feed-in | Both grids | Feed-in | 82.5 | 60.8 | Extra capacity Bargermeer (Enexis) plus Deelnet Emmen and Veenoord Boerdijk (TenneT), 2030 regional; 2031 to 2034 transmission, indicative | high | source, 2026-07-05 |
| Norg (Zeyerveld) service area, feed-in | Both grids | Feed-in | 207 | 125 | Extra capacity Zeyerveen (Enexis) plus Zeyerveen 220 kV transformers (TenneT), 2026 to 2030, indicative | high | source, 2026-07-05 |
| Hoogeveen service area, both directions | Regional (DSO) | Both | 103.8 | 86.7 | New HS/MS station (Rendo) plus extra capacity Hoogeveen (Enexis), 2027 to 2030, indicative | high | source, 2026-07-05 |