Data

Dutch grid congestion in numbers

A short set of verified figures on Dutch grid congestion, from two separate national reports plus two region figures. Every row links its primary source and carries the date Wattlas last verified it.

Aansluitoffensief, 4 February 2026 (standing 1 July 2025)

FigurePrimary sourceVerified
14,044 requests on regional DSO waiting lists for off-take, totalling just over 9 GW (letter page 5, standing as of 1 July 2025 per the letter itself) Kamerbrief Aansluitoffensief netcongestie, 4 February 2026 (Minister Hermans) 2026-07-04
TenneT waiting list: 212 requests, totalling 38 GW (letter page 5, same 1 July 2025 reference date) Kamerbrief Aansluitoffensief netcongestie, 4 February 2026 (Minister Hermans) 2026-07-04
The three largest regional DSOs, plus TenneT, each run at least one regional flex tender in 2026 (letter page 4) Kamerbrief Aansluitoffensief netcongestie, 4 February 2026 (Minister Hermans) 2026-07-04
The FGU region (Flevopolder, Gelderland and Utrecht) keeps the highest urgency in the national approach: the letter states that large grid-capacity shortfalls there must be resolved before measures create room to connect new users (letter page 2) Kamerbrief Aansluitoffensief netcongestie, 4 February 2026 (Minister Hermans) 2026-07-04
According to Stedin, the province of Utrecht needs 320 MW of flexible capacity through 2033 Stedin, provincie Utrecht congestie en congestiemanagement 2026-07-03
Stedin's 30 March 2026 update states a forecast off-take shortfall in the Rotterdam harbour region: 9 MW from 2027, rising to 64 MW in 2030 Stedin press release, update netcongestie havenregio Rotterdam, 30 March 2026 2026-07-04

LAN spring 2026 progress report, 2 April 2026 (standing 31 December 2025)

A later, separate report. These figures are a different snapshot from a different date than the table above; the waiting-list numbers in particular sound similar but are not the same measurement, so they are kept in their own table rather than merged.

FigurePrimary sourceVerified
Regional DSO waiting list for large-user (grootverbruik) off-take connections: just over 15,000 requests, standing 31 December 2025, up about 1,000 in half a year (letter page 3) Kamerbrief Voortgang aanpak Netcongestie, 2 April 2026 (Staatssecretaris De Bat) 2026-07-05
TenneT's waiting list for the national high-voltage grid fell to 211 applicants, standing 31 December 2025, after a clean-up of the list (letter page 3) Kamerbrief Voortgang aanpak Netcongestie, 2 April 2026 (Staatssecretaris De Bat) 2026-07-05
The number of signed Blokstroom (block-hour) flexible contracts tripled to 142, up from 41 in 2024 (letter page 3) Kamerbrief Voortgang aanpak Netcongestie, 2 April 2026 (Staatssecretaris De Bat) 2026-07-05
TenneT's time-of-use grid tariffs, in effect since 1 January 2025, cut average monthly peak load among high-voltage customers by 7.1% in the first half of 2025 (letter page 4) Kamerbrief Voortgang aanpak Netcongestie, 2 April 2026 (Staatssecretaris De Bat) 2026-07-05
The ACM's revised national priority framework for connection queues, giving priority to congestion easers and requests with major societal importance, took effect 31 December 2025 (report page 41) Derde Voortgangsrapportage LAN, April 2026 (Netbeheer Nederland data) 2026-07-05
2,424 kilometres of medium-voltage cable were laid in 2025, up from 1,812 km in 2024 (report page 26, sourced there to Stand van de Uitvoering, March 2026, Netbeheer Nederland) Derde Voortgangsrapportage LAN, April 2026 (Netbeheer Nederland data) 2026-07-05
2,015 kilometres of low-voltage cable were laid in 2025, up from 1,938 km in 2024 (report page 28, sourced there to Stand van de Uitvoering, March 2026, Netbeheer Nederland) Derde Voortgangsrapportage LAN, April 2026 (Netbeheer Nederland data) 2026-07-05

Source attribution

The Aansluitoffensief figures come from the Kamerbrief Aansluitoffensief netcongestie of 4 February 2026, signed by Minister Hermans, fetched directly from open.overheid.nl and checked row by row on 4 July 2026. The LAN progress-report figures come from the Kamerbrief Voortgang aanpak Netcongestie of 2 April 2026, signed by Staatssecretaris De Bat, and its attached Derde Voortgangsrapportage LAN, both fetched directly from open.overheid.nl and checked on 5 July 2026. The Utrecht figure comes from Stedin's own province page, and the Rotterdam harbour figure from Stedin's press release of 30 March 2026, additionally reported by Solar Magazine on 7 April 2026. Figures that could not be confirmed against a primary source are not shown on this page. The "Verified" column is the date Wattlas last checked the row against the linked source; the sources themselves may carry earlier reference dates, which are then named in the row.

Want the region-level detail?

These national numbers set the frame; decisions happen region by region. See the Netherlands grid monitor for status per province, or the Wattlas Issues for the source-locked analysis behind them.